7 Tesla  MRI Expansion Project

Site preparations have begun for the next MCW campus building, an expansion of the existing MRI addition south of the MACC Fund Research Center. This latest addition will house a 7T (7 Tesla) MRI machine. This MRI will be the first of its kind for GE (an active-shielded 7T MRI).

During the last few days, preparations for excavation have occurred, including the erection of a fence to mark the construction site and a silt fence to contain soil and materials runoff. The construction will span from October 2011 through September of 2012 with the following planned phases:

  • September 27 – October 15 Site Preparation
  • October 16 – October 28 Building Foundations Excavation
  • November 3 – December 12 Foundations and Backfill
  • December 13 – January 12 Building Structure and Enclosure
  • January 13 – February 3 Mechanical/Electrical/Plumbing Rough-ins
  • January 13 – February 24 Equipment Installation
  • February 3 – April 4 Interior Finishes

The above dates are tentative, and may change due to weather conditions or materials delays, but serve as a guide to the activities you will observe on the site.

 

October 2012

Left to right:  On the left, a cabinet in the 7T Equipment Room houses a gradient chiller. The other cabinet on the right

contains RF electronics. Insulation panels are next to it.

Week 30

 

 

Week 20

 

Week 17

 

 

Week 16

Week 14

Week 13

 

Week 12

Week 11

Week 10 

 

Week 9

 

Week 8

Week 7

 

Week 6

Week 5

 

 

Week 4

 

Week 3 

Week 2

Week 1

7T week1_ground_breaking 7T_groundbreaking_photo2

 